Construction of casting material before should strictly check the following:
1. Casting material construction is made of steel or hard wood
templates are available. The template must be of adequate strength, good
rigidity, not out of shape, do not shift, no leakage of slurry. Steel
template to mold release agent. Wood template to brush waterproof paint.
The repeated use of the template to cleaning, painting can be used.
2. Water, pouring material should be strictly according to the
manual control, shall not exceed the limit. Under the premise of
ensuring the construction performance, the amount of water should be
less than.
3. Castable refractory mixing time should not less than 5 minutes.
The operation to the use of forced mixer. Mixing should first dry mix,
then add 80% dosage of water mixing, and then depending on the extent of
wet and dry, gently stir until the remaining water, obtaining suitable
work consistency so far. Stirring casting material different should
first mixer clean.
4. Pouring material must use the whole barrel bag full of. Stirring
casting material generally good must be used within 30 minutes. Drying
at high temperature working environment should be appropriate to shorten
this time. Already first castable coagulation even caking not poured
into the mould, nor of mixing water reuse.
5. If the project inspection unqualified should deal with qualified
rear can construction. Expired materials shall not be used. Construction
of castable to ensure that no power outages not interrupted
construction.