During the construction of refractory castable, special
attention should be paid on pin welding, asphalt brushing, stirring of castable
with water, making and fixing of mould, vibration and ramming of castable,
demoulding, sizes’ and measuring points’ accuracy, etc. http://www.yilongrefractory.comDo construction strictly as material manufacturer and boiler works required.
1. Installation of Pin and Claw Nails
Reinstall the pins missing for any
reason and the pins in the area of heating surface composite melding junction
before hydraulic pressure. Lengthen
and reinstall the pins properly in coal mouth, material return mouth and upper inflection
point of air duct furnace so that meets the required density of pins. Brush all
the pre-buried metal parts and claw nails with asphalt paint (thickness > 1mm) or cover them with combustibles
before casting.
2. Dosing and Stirring of Castable & Water
The dosing of castable and water
should be done strictly as the instructions of material manufacturer. The water
should be clean, such as drinking water, ph 6-8. The mixer should be clean forced
action mixer, and clean it for the
next time using. Pay attention on the adding order of castable and water and
its stirring time, adding water freely and prolonging of stirring time are forbidden.
The water and castable should be mixed evenly and stirred till smooth. Carry
away the mixed casatble immediately after stirring, the castable poured out
from stirring tank is disallowed to be poured into the tank and stirred again.
Clean the tank after every construction for the next using, record the amount
of water and castable, and the stirring time.
3. Checking Before Making Template
Check carefully whether the pin, hook
nail and strutting part conform to the drawing, whether all the re-welding and
is done and firm, whether the temporary
metal parts have been cut off. Check whether the metal parts which should be
brushed with asphalt paint meet the requirement, whether the casting place is
clean, any other unrelated materials are forbidden to appear. For easy
demoulding, a thin tier of partition (such as used
oil) can be brushed in the mould. There can not be gaps between each two
templates to avoid castable leaking out, so that also convenient for mould
releasing. The refractory castable should be used up in 30 minutes after
stirring, and should be casted to the required thickness in 1 time. Ram the
castable till tight. For the too thick parts, cast tier by tier, while casting
the upper tier, vibration bar can not touch the lower casted tier.